Something unusual is happening to the American power grid. After roughly two decades of flat electricity demand, the country is suddenly short on power, and the biggest single reason is the race to build data centers for artificial intelligence and cloud computing. That race is starting to affect places you wouldn’t expect it to, including the monthly electric bill of a family in a quiet subdivision and the construction schedule of a new home that just needs a transformer set.

We dug into the federal research, the grid operator data, and what is happening right here in the Black Hills region to answer a question we hear more and more: what does all of this mean for homeowners and builders?

4.4%Share of all US electricity consumed by data centers in 2023 (LBNL)
~12%Potential share by 2030 under central federal lab projections
+31.6%Rise in the average US residential electric rate, 2020 to 2025 (EIA)

Data Center Electricity Use Has Tripled, and It Is Projected to Double or Triple Again

A team from Lawrence Berkeley National Laboratory (a US Department of Energy lab) conducted a benchmark study. Their 2024 report discovered that data centers had been consuming exponential hours of electricity, jumping from 58 terawatt hours in 2014 to 76TWh in 2018 to 176TWh in 2023. That 2023 number alone accounts for about 4.4% of all electricity used in the US through the year. And unfortunately, those numbers are only going to grow.

The following year, those projections became even higher, with people believing that data centers would be responsible for consuming between 9.5 to 15.3 percent of America’s annual electricity. For perspective, a single large AI campus can draw as much power as several hundred thousand homes.

US Data Center Electricity Consumption, 2014 to 2028

Terawatt hours per year. Shaded band shows the federal lab’s 2028 projection range. Hover or tap the points.

YearData center electricity useShare of US total
201458 TWhAbout 1.9%
201876 TWhAbout 1.9%
2023176 TWh4.4%
2028 (projected)325 to 580 TWh6.7% to 12%
2030 (projected)Central scenario11.8% (range 9.5% to 15.3%)

Source: Lawrence Berkeley National Laboratory, 2024 US Data Center Energy Usage Report and 2025 Update, published for the US Department of Energy.

Why a Server Farm Hundreds of Miles Away Shows Up on a Home Electric Bill

Your utility bills you for more than the electricity you use. Baked into rates are the costs of power plants, transmission lines, substations, and capacity payments that guarantee enough generation exists to cover the hottest and coldest days of the year. When enormous new loads connect to a regional grid, it affects everyone. The shared costs rise throughout the country and usually hit households the hardest.

The clearest example in the country is PJM, the grid operator covering 13 states from Virginia to Illinois, home to the world’s largest concentration of data centers. PJM runs an annual capacity auction that pays power plants to be available during peak demand. For the 2024/25 delivery year, that capacity cleared at $28.92 per megawatt day. However, only a year later it cleared at $269.92 and the year after that $329.17, pinned at a federally approved price cap. The following auction hit the cap again.

PJM Capacity Auction Clearing Price

Dollars per megawatt day, by delivery year. The 2026/27 result cleared at a regulatory price cap.

Delivery yearClearing price (per MW-day)
2024/25$28.92
2025/26$269.92
2026/27$329.17 (at price cap)

Source: PJM Interconnection base residual auction results. PJM’s independent market monitor, Monitoring Analytics, attributed 63% of the 2025/26 price increase to data center demand, roughly $9.3 billion recovered from customers in a single year.

As a result of these audits, households in the PJM region have been hit with increases at roughly $10 to $21 per month, depending on what zone they’re in, and those increases don’t seem like they’re going to stop anytime soon. Analysts estimate many PJM households are paying on the order of $25 to $30 more per month than they were two years earlier, largely because of capacity costs.

While the effect has been less substantial nationally, it’s still visible. A National Association of Realtors analysis found residential electricity rates rose 21.4 percent from 2020 to 2024 in counties with ten or more data centers, compared with 15.7 percent in counties without them. Though, researchers are careful to note that the data centers are only one driver among several, including fuel prices, grid hardening, and aging infrastructure replacement, and a Rutgers study found little effect at the ZIP code level so far in some markets. Data centers are not the sole reason bills are rising, but they are a measurable and growing one, especially in regions with heavy buildout.

Residential Rate Growth Near Data Centers, 2020 to 2024

Increase in residential electricity rates by county type. Hover or tap the bars.

County typeResidential rate increase, 2020 to 2024
Counties with 10 or more data centers+21.4%
Counties without data centers+15.7%

Source: National Association of Realtors analysis of EIA data, as reported in 2026 housing cost coverage.

The National Trend: Residential Rates Are Climbing Faster Than Inflation

Zoom out and the direction is unmistakable. The US Energy Information Administration’s data shows the average residential electricity price climbing from 13.15 cents per kilowatt hour in 2020 to 17.30 cents in 2025, a 31.6 percent nominal increase in five years, with the national average sitting around 18.3 cents by late 2026. Adjusted for inflation, household electricity is now more expensive than at any point since the mid 1990s.

Average US Residential Electricity Price

Cents per kilowatt hour, annual average. 2026 shows the latest monthly reading. Hover or tap the points.

YearAvg residential price (¢/kWh)
202013.15
202113.66
202215.04
202316.00
202416.48
202517.30
2026 (Oct reading)18.34

Source: US Energy Information Administration, average retail price of electricity, residential sector.

Closer Than You Think: Data Centers Are Arriving in Our Region

It’s tempting to ignore this issue, but it’s become impossible. The utility holding company headquartered in Rapid City, Black Hills Corp, has become one of the more active data center players in the Mountain West. It already serves a major social media company’s data center in Cheyenne, it announced a $1.8 billion plan to build 564 megawatts of new generation between 2027 and 2029 to serve a planned Google data center there, and it has said its pipeline of large load requests has grown from over 1 gigawatt to more than 3 gigawatts. Its Wyoming electric utility has set repeated all time peak load records driven primarily by large load growth, including a July 2026 peak 16 percent higher than the year before.

Closer to home, a developer has proposed a 15 megawatt data center at the Black Hills Industrial Center in Rapid City. State officials have been openly debating how, and whether, South Dakota should court the industry. They’ve even gone as far as studying nuclear options for future large loads. For scale, South Dakota’s largest existing data center draws about 30 megawatts, while the largest AI campuses elsewhere in the country run from hundreds of megawatts up to a gigawatt, equivalent to the consumption of hundreds of thousands of homes. Regional utilities have also pointed to data center demand as part of the reasoning behind consolidation and new generation buildouts across the Dakotas, Montana, and Wyoming.

In other words, the forces reshaping grids back east are beginning to shape planning decisions, generation investments, and rate cases in our own backyard. How much of that cost lands on households depends heavily on how regulators structure contracts with large customers, which is exactly the debate playing out in state capitols right now.

What It Means for Homeowners

1. Plan for power that costs more, and make efficiency pay

With every projection pointing towards major increases, it’s a good time to start thinking of ways to reduce the amount of power you consume. That means making changes to your home like LED lighting throughout, ensuring you have the right size equipment, and smart control of big loads. You can’t be charged for power you don’t use.

2. Take reliability into your own hands

Grid operators across the country are warning that reserve margins are tightening as demand growth outruns new generation. PJM set record prices and still fell short of its planning reserve margin. When the grid runs tighter, weather events bite harder. For rural Black Hills properties, where an outage can also mean no well pump and no heat circulation in January, a properly installed standby generator with an automatic transfer switch has shifted from a luxury to a genuinely practical hedge.

3. Home EV charging still wins, if the installation is done right

Even at 18 cents per kilowatt hour, charging at home remains far cheaper per mile than gasoline, and our regional residential rates sit below the national average. The real risk is on the installation side: EV charging is a heavy continuous load, and the circuit sizing, receptacle quality, and conductor ampacity matter far more than the brand of charger. That is where a licensed electrician earns their keep.

4. Think about panel capacity before you need it

Between EV chargers, hot tubs, shop circuits, and electric heat, homes are being asked to carry more load than ever. If your service or panel is already near it’s limit, be sure to schedule an upgrade before buying a new appliance that forces the issue, especially with electrical equipment prices trending up.

What It Means for Builders and General Contractors

The quieter consequence of the data center boom is a strained electrical supply chain. Data centers, grid expansion, and fleet replacement are all relying on the same supplies of transformers, switchgear, and breakers. As demand rises, the lead times have grown from months to years for some equipment. Many homebuilder groups have had to delay projects waiting for a transformer, and utilities in several states have warned that new housing developments may depend on the availability of grid equipment.

For new construction in a growing region, the practical takeaways are:

  • Engage the utility early. Service applications, transformer requests, and meter sets should be moving while the foundation is going in, not after drywall.
  • Lock in the electrical scope early. Late changes to service size or major circuits are harder to absorb when equipment has lead times.
  • Work with an electrical contractor who schedules tightly. When the utility side of the timeline is less predictable, the contractor controlled side has to be more predictable. Continuous rough in trips, clean coordination with other trades, and committed dates matter more in this environment, not less.
  • Future proof the service. Spec for the EV charger, the shop, and the hot tub the buyer will want in five years. Conduit and capacity are cheaper to set up during construction than after.

Common Questions

Are data centers the reason my electric bill went up?

Partly, and it depends on where you live. In the 13 state PJM grid region, independent analysis attributes billions of dollars in recent capacity costs primarily to data center demand, worth roughly $10 to $30 per month on household bills in some zones. In our region the effect so far is smaller and more indirect, flowing through fuel costs, new generation investment, and regional market prices. Fuel prices, grid hardening, and aging equipment replacement are also significant drivers everywhere.

Will data centers in the Black Hills raise local rates?

That depends largely on how contracts with large customers are structured. Regulators can require large loads to pay for the generation and transmission built to serve them, which shields other customers, or those costs can be shared more broadly. This is an active policy debate in South Dakota and neighboring states right now, which is a good reason for homeowners to pay attention to utility rate proceedings.

Does rising demand mean more outages?

Not automatically, but tighter reserve margins leave less cushion during extreme weather and plant outages. Grid operators across the country have flagged shrinking margins as demand grows faster than new generation connects. For households that cannot afford downtime, backup power is the most direct protection available.

Is home EV charging still worth it with higher rates?

Yes. Even after recent increases, charging at home typically costs a fraction of the equivalent gasoline cost per mile, and regional residential rates remain below the national average. The bigger consideration is a safe, properly sized installation, since EV charging is one of the heaviest continuous loads in a home.

Planning Electrical Work in a Changing Grid?

Whether you are sizing a panel for an EV charger, adding standby power, or scheduling electrical for a new build, Wires R Us has served the Black Hills region since 1999 with clean, efficient, code compliant work and committed timelines. Let’s plan it right the first time.

Get in Touch

Sources

  • Lawrence Berkeley National Laboratory, 2024 US Data Center Energy Usage Report and 2025 Update (US Department of Energy)
  • US Energy Information Administration, average retail price of electricity by sector
  • PJM Interconnection, base residual auction results; Monitoring Analytics independent market monitor reports
  • IEEFA, Projected data center growth spurs PJM capacity prices by factor of 10
  • National Association of Realtors analysis of county level electricity rates, 2020 to 2024
  • CISA National Infrastructure Advisory Council, Addressing the Critical Shortage of Power Transformers
  • Black Hills Corp investor releases and 2025 annual report (Wyoming generation plan, large load pipeline, peak load records)
  • South Dakota Searchlight and regional reporting on proposed Rapid City data center development and state energy policy

Ready to work with a team that values cleanliness, reliability, craftsmanship, and efficiency?

Seraphinite AcceleratorOptimized by Seraphinite Accelerator
Turns on site high speed to be attractive for people and search engines.